Mount Construction was awarded this project by the Camden County Municipal Authority to rehabilitate and replace 8200 linear feet of sewer force main that was consistently requiring emergency repairs.
Project involved slip lining of 6400 linear feet of 16” sewer with 14” IPS HDPE fused pipe and installation of 1800 linear feet 16” DIPS HDPE pipe via open cut. During installation, emergencies continued to occur along the pipeline as leaks would form in areas as other areas were rehabilitated. Mount Construction was able to address these areas immediately for the CCMUA avoiding hardships to the residents and the environment. Mount was able to deliver this project under budget and on time.